Door Order Lead Time for Contractors: Scheduling Iron and Aluminum Doors

t409-7

t409-7

Door order lead time for contractors is the full period from the first inquiry to installed doors, and it is set by measurement, written approval, factory production and finishing, not just by the time spent in the workshop. Contractors who send photos and confirm measurements early, then approve the drawing quickly, give the factory the clearest path to a reliable installation date.

What makes up the lead time

A door order does not start on the day production begins. The timeline usually includes the inquiry with photos, the on-site measurement, the drawing and written specification, your approval, the production in our factory, the finishing, and finally the installation on site. Each stage depends on the one before it, so a delay early in the chain moves everything that follows.

When you plan your schedule, count all of these steps instead of only the workshop days. This gives a more honest picture of when the doors can realistically be on site.

How measurement affects your schedule

Accurate measurement is the foundation of any door order. If the opening is measured before plastering, tiling or floor finishing is complete, the door may not fit once those layers are added. For this reason we recommend measuring at the stage the contractor specifies as final for the opening.

  • Measure each opening at the stage agreed with the site team
  • Note the swing direction and the side of the hinges
  • Send photos with dimensions written on them

Clear measurements reduce the back and forth that often causes the biggest delays.

Approval and why it matters

The drawing and written specification must be approved before production starts. Approval covers the profile, the infill, the finish and any hardware details. A change requested after production has begun can mean reworking parts, which adds time to the schedule.

We suggest setting an internal deadline for approval within your project plan, and sharing the drawing with the architect or interior designer at the same time, so that any design comments arrive in one round.

Finishing steps that take time

Iron and aluminum doors often go through finishing steps that need their own time window. Hot-dip galvanizing and powder coating are the main ones. These processes protect the metal, but they must be scheduled around the rest of the production queue, so they should be included in your planning from the start.

If the door has a specific colour or a special finish for the building, tell us early so the finishing step can be planned in advance.

Coordinating installation with site work

Installation is the last step, and it depends on the site being ready. Frames must be plumb, openings must be clear, and the floor and surrounding work should be at the stage agreed for fitting. If the site is not ready when the doors arrive, the doors may have to wait, which affects both the installation and the rest of your sequence.

Confirm the installation date with the site supervisor before the doors leave the factory, and keep a clear access route for delivery.

Building a realistic delivery schedule

A practical schedule for contractors starts from the installation date and works backwards. Add a buffer for approval rounds, finishing and transport, and avoid planning a door delivery on the same day the opening is first ready. Keep the schedule shared with your team so everyone knows which step each person is responsible for.

Exact production durations depend on the order, so we confirm the expected timing with you after the drawing is approved.

Frequently asked questions

How early should a contractor send the door order?

Send the inquiry as soon as the openings are known and the design is close to final. Early photos and measurements let us start the drawing sooner, which protects your schedule.

Can measurements be taken before the walls are finished?

It is possible, but the final opening size must account for plaster, tiles or floor finishes. We recommend measuring at the stage your site team considers final for each opening.

What causes most delays in door orders?

The most common causes are late measurements, changes requested after approval, and site readiness issues at installation. Clear information and a fast approval round prevent most of them.

Do you confirm delivery dates in writing?

Yes, we confirm the expected timing in writing after the drawing and specification are approved, so you can align it with your project plan.

Common mistakes to avoid

The most common mistake is measuring too early and not allowing for the finish layers added later. Another is requesting design changes after approval, which can reopen production steps already in progress.

Our recommendation

Set your approval deadline and your site-readiness date first, then work backwards so that measurement, drawing and finishing each have a fixed window in the schedule.

Summary

Door order lead time covers measurement, approval, production, finishing and installation, so planning all of these steps gives contractors a reliable delivery schedule.

Send us your openings with photos and dimensions, and we wil