top of page
‹ חזרה

Glass Partition Lead Time: Stages from Measurement to Installation

t432-18

t432-18

The glass partition lead time is made up of distinct stages: on-site measurement, drawing and written specification, client approval, factory production and finishing, then installation. Most of the schedule depends on how quickly the measurements and approvals are settled, so planning those early protects the installation date.

Stage 1: Inquiry and On-Site Measurement

Every glass partition project starts with an inquiry that includes photos and a rough description of the space. Once that is received, a technician visits the site to measure the opening, check the floor and ceiling levels, and confirm where the partition will meet walls, columns or existing frames.

  • Measure at the actual site, not from old plans
  • Note door swing, handle positions and cable routes
  • Confirm whether the floor is finished or still being poured

Measurements taken before finishing works are the most common source of delay, so they should be repeated when the surrounding trades are complete.

Stage 2: Drawing and Written Specification

After measuring, the factory prepares a drawing and a written specification covering the frame profiles, glass type and thickness, fittings, sealing and the finish. This document is what the client approves, so it should match the layout the designer intends.

Checking the drawing carefully at this point saves time later. Any change requested after production starts usually means remaking parts, which extends the schedule.

Stage 3: Client Approval and Ordering

Production begins only after the client signs off on the drawing and specification. Approval includes the glass finish, the frame colour and any hardware choices. For projects involving a building committee or an architect, allow extra time for their review cycle.

What speeds approval

Send one consolidated set of comments rather than several separate messages. Confirm the final dimensions in writing so that the drawing reflects the site, not an earlier estimate.

Stage 4: Factory Production and Finishing

Once approved, the profiles are cut and assembled in the factory at 37 Rival Street, Tel Aviv, and the glass is prepared to the specified sizes. If the frame needs a protective finish, such as hot-dip galvanizing or powder coating, it is processed before assembly. Coating and curing add time that should be built into the schedule.

Production time depends on the size and complexity of the partition, the number of units in the order and the current workload in the workshop. Ask for a schedule with clear milestones rather than a single end date.

Stage 5: Delivery and Pre-Installation Check

Before the partition goes to site, the components are checked against the approved drawing. Glass is packed to avoid edge damage, and the frame sections are labelled so that installation proceeds in the right order.

A short check on site before the crew arrives confirms that the floor is level, the openings are clear and the access route for the glass is open. This simple step prevents a wasted installation visit.

Stage 6: Installation and Handover

Installation fixes the frame, sets the glass panels, seals the joints and adjusts the door or sliding elements. The crew tests movement and locking before leaving. Handover includes a walk-through of how to clean the glass and care for the finish.

  • Confirm the floor and wall finishes are complete
  • Keep the area clear of other trades during fitting
  • Inspect the sealing and hardware at handover

Frequently asked questions

How long does the glass partition lead time usually take?

The total depends on measurement timing, approval speed, production workload and finishing. Your project manager should provide a schedule based on your specific order rather than a fixed figure.

Can I start installation right after measuring?

No. Measuring comes first, then the drawing, approval and production. Installation follows only after the parts are finished and checked.

What is the most common cause of delay?

Changes to dimensions or design after production has started, and measurements taken before adjacent works are finished, are the usual causes.

Should I measure again before installation?

Yes, it is wise to confirm openings and levels once the surrounding finishes are complete, especially if the site was measured early in the project.

Common mistakes to avoid

Ordering before the site is measured and approved, or changing the design after production starts, both extend the schedule. Clear measurements and an early sign-off avoid most of the delay.

Our recommendation

Share the final floor and wall finishes with the factory before drawing approval, and request a stage-by-stage schedule with milestones so each step can be tracked.

Summary

A glass partition moves through measurement, drawing, approval, production, finishing and installation. Settling measurements and approvals early keeps the whole schedule on track.

Send us photos and your site details to start the measuremen

השאירו פרטים ונחזור אליכם

עוד מדריכים ודפים בנושא

bottom of page
הקבוצה שלנו: 🛒 החנות האונליין — סורגים ומסגרות🏠 קובי אלקיים נדל"ן בע"מ